| DATE |
CONTENT |
|
Feb,1999
|
The First preparatory meeting held. |
|
May,1999
|
Application to tender accepted. |
|
May,2000
|
Selected as the best applicant. |
|
Dec,2000
|
Initiator Conference and first meeting of the Board members. |
|
Dec,2000
|
Obtained company licence. |
|
Jan,2001
|
Signing
of the "Construction and Operation Agreement" and the"Development
Agreement" with Kaohsiung Municipal Government |
|
Aug,2001
|
Sign
Contracts with Siemens AG for Rolling Stocks,
Signalling System,DC Power Supply System,and E&M Poject Management |
|
Oct,2001
|
Ground-breaking
ceremony for Red Line R3 Station |
|
Oct,2001
|
The
Ministry of Transportation and Communications approved the project
starting date of the Red and Orange Lines of Kaohsiung Rapid Transit
System |
|
Nov,2001
|
Ground-breaking
ceremony for the Red and Orange Lines O5/R10 Station |
|
Jan,2002
|
The paid-in capital
reached 10 billion New Taiwan Dollars and cash raising from stock
issue completed |
|
Jun,2002
|
General contracts
for CR1、CR3、CR4、CO1 concluded |
|
Jul,2002
|
General contract
for CR2 concluded |
|
Sep,2002
|
General contracts
for CR5、CR6、CR7、CO2、CO3、CO4 concluded |
|
Nov,2002
|
The
civil general contracts for Depot CD2、CD3 concluded |
|
Nov,2002
|
The
ceremony for the readiness of shield machine"Happy#1" was
held in R3 station |
|
Dec,2002
|
Signed
Contract for Platform Screen Door System and Depot Equipment |
|
Jan,2003
|
Signed
Contract for Escalator 、Elevator and Communication System |
|
Jan,2003
|
Signed
the syndicated credit facility agreement in the total amount of NT
19.8 billion. |
|
Mar,2003
|
Signed
Contract for Track Work and Power Supply System |
|
Mar,2003
|
Ground-breaking
ceremony for the Red and Orange Lines in Kaohsiung County. |
|
Apr,2003
|
Signed
Contract for Automatic Fare Collection System. |
|
Apr,2005
|
The
breakthrough of all the shield tunnels from R3 to R8 Station is accomplished.. |
|
May,2005
|
Train
No.1 rolled out from Siemens SGP Verkehrtecknik in Vienna, Austria. |
|
Oct,2005
|
The
first shipment of Train arrived at Kaohsiung Port. |
|
Dec,2005
|
Reached
the first milestone of Construction and Operation Agreement - running
test on the main line between South Depot and R4 Station. |
|
May,
2006
|
The
breakthrough of all the shield tunnels on the red and orange lines
is accomplished. |
|
Sep,
2006
|
Operation
Control Center open ceremony |
|
Apr,
2007
|
The
CR2 section was awarded 2007 Public Construction Safety and Health
Award held by Council of Labor Affairs, Executive Yuan. |
|
May,
2007
|
126
cars have arrived at South Depot. |
|
Sep,
2007
|
R3
to R8 initial inspection. |
|
Oct,
2007
|
Red
line trial run. |
|
Nov,
2007
|
R3
to R8 final inspection. |
|
Jan,
2008
|
R9
to R23 initial inspection. |