Orange Line CO2 Section General Contract

Contract Scope CH115+059 ~ CH116+961
Route Length 1.903 kilometers
Commencement Date October 2002
Due Date October 2007

 

Contract Abstract:
Along Jungjeng Road, the alignment starts eastward from the O6 Shin Yi Primary School Station located at the intersection between Jungjeng 3rd Road and Jintian Road, then passing O7 Culture Center Station and terminates at the eastern end of O8 Wukuaitsuo Station in Fude 2nd Road. The work includes 3 underground station and 2 bore tunnels with a total length of about 1,300 meters.