Red Line CR4 Section General Contract

Contract Scope CH249+855 ~ CH250+652
Route Length 0.797 kilometers
Commencement Date April 2002
Due Date October 2007


Contract Abstract:
The CR4 Section is located at the intersection of Red Line and Orange Line. The work includes underground transfer station O5 / R10, approximately 1,300 meters cut & cover tunnels and 2 bore tunnels with nearly 900 meters in length. Along the Jungjeng 1st Road, the eastward corridor travels from the eastern end of O4 City Council station, passes through Junghua 3rd Road, Jungshan 1st Road and Linsen 1st Road etc., finally terminates at Jintian Road before the O6 Shin Yi Primary School Station. The northward corridor starts from southern end of O5 / R10 station, goes along Jungshan 1st Road and crosses Chishian 2nd Rd until reaching Jianguo 3rd Road, and stops before R11 Kaohsiung Train Station.
BACK