Overview
of Civil Contracts
The main civil contracts of the Red and Orange Lines of Kaohsiung
Mass Rapid Transit Project consist of 11 general contracts for the
red and orange lines and 3 general contracts for the depots (as graph
below). The scopes of each general contract include civil works, environmental
control, water and electricity, and public arts, etc. The general
contractor is responsible for both design and construction works,
that is in turnkey model. The contracts provisions, which request
contractors to be responsible for design, construction and acceptance
inspection, are based on "Rapid Transit Construction Specification"
published by Construction Specification Integration Center of Public
Construction Commission and "Conditions of Contract for EPC/Turnkey
Projects" published by International Federation of Consulting
Engineers (FIDIC). ¡@¡@ |
|
|