|
|

The civil systems consist
of civil construction works and civil engineering design.The civil
costruction works for the Kaohsiung Rapid Transit System Red and Orange
Lines mainly consists of the construction of stations, tunnels and
elevated line sections, and depots. The civil engineering design scope
covers the precise alignment of the routes, track works,geotechnical
works, tunnels and other underground structures, road works, drainage,
viaducts, and
architectural works.
The main construction methods
used for the project are as follows: |
| 1. |
Cut and Cover
Construction(Cut
and Cover Construction illustraion
)
This construction method, whereby the site is fully excavated, the structure built
and then covered over, uses diaphragm walls as temporary retaining walls within
the site area. The sequence of work is: |
| Step
one : |
Construction
of diaphragm walls, pin piles, and decking. |
| Step two
: |
Excavation
within the diaphragm walls, installing struts as work progresses. |
| Step
three : |
Construction
of permanent floor slabs and walls. |
|
Step four :
|
Fitting out the internal structures, backfilling,
and reinstating the surface structures.
|
| This method is primarily used for
construction of underground stations, crossover tunnels, and areas where the geological
conditions are unsuitable for shield tunnels, and is widely used both domestically
and overseas. The construction will be carried out in sections in order to minimize
disruption of traffic flow. The excavation and the construction of the underground
structures will then be carried out below the temporary surface deck. This construction
method will be used for 28 underground stations, 17 sections of line, and 2 open-air
sections where the conditions are not appropriate for tunnelling. |
| 2. |
Shield
Tunnelling(Shield
Tunnelling illustration )
This method involves the use of shield machine to drive the tunnels below the
ground. After completion of a work shaft, the shield machine is lowered into the
shaft and assembled there before excavation and construction of the tunnels using
precast concrete lining segments of about 1.2 meter width. On completion of a
tunnel drive, the shield machine will be dismantled and hoisted out via another
work shaft for reuse. This construction method causes minimal disruption to traffic
and the environment because all the work takes place below ground and the ground
level environment is unaffected. Thirty-two sections of tunnel, or the total line
length of 22,738 meters, will be built using this construction technique. |
|
The track gauge of the Kaohsiung Rapid Transit System
will be 1435 mm. The track will use UIC 60 rail and elastic supporting
system to absorb vibrations and minimize noise. The design speed
for the main line is 90 km/hr, although the maximum operating speed
will be 80 km/hr. In depots, the design speed will be reduced to
35 km/hr and the operating speed will be 25 km/hr.
|
|
Safety, Hygiene
and Environmental Protection
|
• |
Safety Policy
The Kaohsiung Rapid Transit Corporation is committed to abide by all
laws and regulations of the nations, eliminate all hazards and continuously
improve its management of safety in order to protect life. |
| • |
Safety
Management |
| |
|
Recognizing the value of life and the
importance of safety, the Kaohsiung Rapid Transit Corporation regards
the safety of passengers, the public and its staff as of paramount
importance. All practicable measures will be taken to assure safety,
and contingency plans will be developed and rehearsed to minimize
the impact from any accident or natural disaster. |
| • |
Environmental Protection |
| |
|
The Kaohsiung Rapid Transit Corporation
will take all feasible measures to protect the environment both during
the construction and the operation of the Rapid Transit System to
assure a high quality living environment in the Kaohsiung area. Measures
will include the reductions of noise and vibration and of air and
water pollution, the management of traffic, and the conservation of
cultural sites and landscapes. The effectiveness of these measures
will be monitored regularly to ensure compliance with our commitments
made in the Environmental Impact Assessment Report. |
| |
|
|
| |
|
|
|
 |